When initial estimates and schedules are prepared, what is typically assumed about resources?

Disable ads (and more) with a premium pass for a one time $4.99 payment

Prepare for the Construction Management Exam. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

When preparing initial estimates and schedules, the assumption of unlimited resources is often used to simplify the planning process. This approach allows project managers to focus on defining tasks, sequencing activities, and determining necessary durations without the immediate constraints of resource availability. By assuming that resources can be accessed freely, planners can create more straightforward and optimistic timelines and cost estimates.

However, it's important to note that this assumption is largely theoretical and may not reflect real-world conditions. In practical scenarios, projects will eventually require a more nuanced understanding of resource limitations and constraints, which will be addressed in later phases of planning and execution. This initial perspective facilitates brainstorming and sets a foundation for comprehensive planning before delving into the complexities of resource allocation.

The other answer choices reflect various levels of resource constraints that may occur during actual project execution but do not align with the conventional approach used in the initial phases of project estimation and scheduling.