Which of the following is an example of an excusable delay?

Disable ads (and more) with a premium pass for a one time $4.99 payment

Prepare for the Construction Management Exam. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

An excusable delay is one that is beyond the control of the contractor and is typically recognized in construction contracts as a legitimate reason for a delay in project completion without penalty. This type of delay usually has provisions that allow the contractor to seek an extension of time.

Inclement weather fits this definition well because it is often unpredictable and cannot be anticipated. Extreme weather conditions, such as heavy rain, snow, or hurricanes, can halt construction activities and are generally accepted in the industry as valid reasons for delaying project timelines. Contracts often include clauses that specifically address weather-related delays, detailing how they can affect the construction schedule.

In contrast, delays caused by subcontractors, material shortages, or miscommunications are generally not considered excusable delays. These delays are usually within the control of the contractor to manage and plan around, making them more challenging to justify as legitimate reasons for extending project completion dates.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy